Wicklow Train Derailment
JCL were requested by Iarnród Éireann to address a train derailment (following a landslide) at Wicklow Station - while there had been no injuries the line was blocked and the embankment which had collapsed was deemed unsafe
Client
Iarnród Éireann, CIE Works, Inchicore, Dublin 8
Consultant
n/a
Location
Wicklow
JCL received a call at 6am on 16/11/2009 and were asked to mobile immediately to Wicklow Train Station to work with the Client, appoint a designer, and safely open the railway line again - JCL were on site at 7am
Key Features
- An existing embankment, discovered to be primarily made up ground, had collapsed during heavy rain and had caused a landslide on top of the tracks immediately adjacent to Wicklow Train Station
- An empty passenger train heading to Dublin collided with the landslide and was derailed
- JCL Engineers assessed the situation and looked at the various options for moving the train back onto the track - this included substaintial liaison with landowners and third parties
- Due to the difficult nature of the load - which has fixed lifting points, some of which were under the soil, JCL carried out a 3D Laser Scan of the train in order to design a lifting methodology which would safely lift the train back onto the tracks
- Creating access down to the railway in order to move the train required 4 30T Excavators and Dump trucks - this had to be filled with 2000m3 of compacted stone to act as a crane access and platform
- A 250T crane was mobilised and moved the train in accordance with the methodology envisaged through the 3D modelling of the derailment
- The tracks were cleared using mini diggers and small plant to ensure the integrity of the line
- The existing embankment and newly created access road and crane platform were filled and reconstructed in accordance to a design proposed by JCL's designers
- The line was opened up initially under a speed restriction, once JCL were far enough removed from the line after 5 days works
- The entire line was open fully and JCL had demobilised off site within two weeks